Water system map.

Metropolitan District Meetings

The Metropolitan District holds meetings via teleconference.

Dial-In Number:  425-436-6331

Access Code:  261328#

NOTICE of meetings of the Board of Directors of Bellyache Ridge Metropolitan District. All times are MT.

  • 6:00 p.m. February 13, 2024 – Regular Meeting
  • 6:00 p.m. May 7, 2024 – Special Meeting
  • 6:00 p.m. June 11, 2024 – Regular Meeting
  • 6:00 p.m. August 13, 2024 – Regular Meeting
  • 6:00 p.m. October 8, 2024 – Regular Meeting
  • 6:00 p.m. December 10, 2024 – Regular Meeting

Metro District meeting materials are available at least 24 hours before each meeting. They can be accessed and downloaded at https://bellyachesubdivision.com.

Water Rates

The following water rates are in effect beginning June 16, 2023.

All water rate information can be found in Appendix B of the Bellyache Ridge Metropolitan District Rules and Regulations – Revision 8.0.

Notices and Resolutions

How-to-Pay: Monthly Water Bill

Bellyache residents looking to pay their water bill: AmCoBi will continue to take payments up to the 15th of May.

www.AmCoBi.com

Metropolitan District Activities

2023

Repair options

2022

In February 2022 some water lines on Little Dipper Road froze because a re-circulation pump was not activated for the winter season. A new pump and a significantly improved control system was installed.

It is expected the re-circulation pump will remain in operation for the long term.

In the summer of 2022, water mains in the Little Dipper cul-de-sac were located for depth. A plan was developed for future excavation and insulation of water mains most at risk. Grant funding is considered necessary to pursue this activity.

2021

Acting on the advice of counsel and water system operators, the Board adopted a resolution declaring a Water Supply Emergency within the Bellyache Ridge Metropolitan District effective October 13, 2021.

In April 2021 the Metro District Board reviewed and began using a Reserve Study for Major Repairs and Replacements Expenditures as a key tool for planning future funding needs.

The exterior of both pump houses were cleaned and stained.

2020

The cedar shake roof on the pump house for wells 1R & 2 was replaced with a standing seam metal roof.

In August 2020 aging galvanized steel plumbing at well 3 was replaced with a modern pipe solution and a drain was added.

In July 2020 the main power supply to pump house 1&2 failed and was replaced.

Periodic water tank inspection reports were completed.

Budget Process

The metro district follows the process and requirements to adopt an annual budget in accordance with the Local Government Budget Law of Colorado, part 1 of article 1 of title 29, C.R.S. A copy of the budget is available for public inspection at the offices of Community Resource Services of Colorado, LLC.

Audits

The metro district has requirements to have an annual audit of the district’s financial statements prepared in accordance with the Colorado Local Government Audit Law, part 6 of article 1 of title 29, C.R.S. A copy of the audit report is available for public inspection at the offices of Community Resource Services of Colorado, LLC.